Job —
← Sign in from the main page SharePoint: Not connected

Search & Edit Existing Job

Job Details

Customer

Dates & Logistics

Materials & Parts

What is issued to this job becomes Section 2 of the worksheet, and what is made on it becomes Section 5. Both are read back out of Stores, so the sheet and the register cannot disagree.

All production jobs not yet closed or cancelled. Click a row to open it for editing.

Job Number Date In Customer Description Qty Working Party Status
Work Sheet
Summary Page
Material Supply Project
Oct 2026
Job / Work Order Number:
Project Type:
Section 1: Project Details
Customer: Order Date:
Customer PO No.: Due Ship Date:
Contact: ESN / MSN / REG:
Shipping Address:
Remarks:
Section 2: Bill of Materials (BOM) (Materials to be used)
(add lines as needed for project)
ItemDescriptionPart NumberQty Serial No.
(note if BFE)
Batch No.Shelf life
1
Section 3: Design Data
Data Reference:
This worksheet is for material supply projects only.Page 1 of 3
Work Sheet
Summary Page
Material Supply Project
Oct 2026
Job / Work Order Number:
Project Type:
Section 4: Production Process Control
4.1 Parts Produced By:
4.2 List tools used
SatisInitial
4.3 Withdraw material(s) from stores and confirm specification against Design Data.
4.3.1 Measure the raw material plate dimensions. Is this I.A.W Design Data? (trimming to fit dimension allowed, if feasible)
4.4.1 Switch on laser unit and allow axis-homing to automatically complete. Do not continue if axis homing fails.
4.4.2 Outline the text area I.A.W the Design Data.
4.4.3 Engrave the plate text I.A.W Design Data.
4.4.4 Is the text location I.A.W Design Data?
4.4.5 Measure main text height and check against Design Data.
4.4.6 Measure the identification markings text height and check against the Design Data.
4.5.1 Once satisfied with the part; turn off the laser.
4.5.2 Turn off the extractor.
4.5.3 Close the laser door.
4.5.4 Place completed part in a protective bag and deliver to inspection bench with this Work Sheet.
Please save and store the production data before continuing.
This worksheet is for material supply projects only.Page 2 of 3
Work Sheet
Summary Page
Material Supply Project
Oct 2026
Job / Work Order Number:
Project Type:
Section 5: Parts Supplied
(add/delete lines as needed for project)
ItemDescriptionPart NumberQty Serial No.Batch No.Shelf life
1
Total Quantity Supplied:
Section 6: Final Item Inspection [In accordance with the Design Data]
PASSFAIL
Materials used are as stated in the Design Data?
Dimensions are as stated in the Design Data?
Colours are as stated in the Design Data?
Part Number is correct as per the Design Data and is clearly legible?
Text is in accordance with the Design Data?
Visual quality is of good standard (clear image & sharp lines)?
Identification markings are present and legible?
Check of agency provided airworthiness and environmental data. SatisNot Satis
Has a recent check of agency provided airworthiness and environmental data been carried out? Check GQ316.
This worksheet is for material supply projects only.Page 3 of 3
Job No:
Aero Production 21 Ltd — Unit 2 Distribution Centre, SFZ, Shannon Airport, Co Clare, Ireland V14 HK22
Phone: +353 61 353 747Email: info@aii.ie • www.aii.ieFax: +353 61 353 737
Job Details
ESTIMATE NO.:PO NUMBER:
QTY MANUFACTURED:ESN/MSN/REG:
JOB DESCRIPTION:
Customer
CUSTOMER:CONTACT:
Dates & Logistics
DATE IN:DATE OUT:
WORKING PARTY:LOCATION:
SHIPPING BY:SHIPPING ACCT:
SHIPPER:AWB:
ADDITIONAL INFO:
AUTHORISED SIGNATURE
DATE